Wednesday, August 8th, 2018 – Storage, Networking & More Tests

Today the team was able to start wrapping up deployment.

We were able to get the following completed:

  • NFS fixed, tuned and mounted on cpus
  • Lustre and client rpms were prepared and be ready tomorrow morning
  • Configured provisional external ip addresses on the head nodes as well as login nodes.
  • Tests were run to for GPFS NFS mount
  • Updates to firmware were done and reapplied BIOS settings to the machines that had motherboards replaced due to the power outage yesterday.
  • Started Linpack tests on another rack pair of rack. This is the last pair!

A Dell technician replaces the mother board on a node that was damaged during the power outage.